The Norwegian Petroleum Directorate (NPD) reviewed five field developments taking place on the Norwegian shelf to uncover the causes of cost overruns in offshore projects over NOK 10 billion ($1.7 billion USD). Their goal was to identify why some developments finish within budget, while others suffer significant cost overruns and then provide recommendations future projects can follow to increase project success rates. Not surprisingly, the report showed that overruns are not specific to Norwegian megaprojects, but are becoming a global issue due to the increase in size and complexity of projects taking place around the world today. In the search for new resources, E&Ps are developing in increasingly remote, deepwater areas and projects are also now more modular-based, requiring multiple scope packages to be managed by multiple global contractors. In addition, the global talent crisis the industry is facing, with an estimated 40% of experienced staff departing in the next 5-10 years, is making it harder and more expensive to find (and keep) skilled workers. With all of these hurdles today, it is increasingly challenging to achieve cost effective developments in isolated and extremely deep locations.
Common Project Success Factors
Notwithstanding specific regional issues, like regulatory requirements, competition for restricted supply chains, local day rates, and labour costs, there are common elements leading costs to skyrocket on all mega capital projects worldwide. Looking at projects that both stayed on budget and those with cost overruns, NPD’s work uncovered the four following main project implementation factors that influence a project’s success:
One discipline seeing a great deal of attention because it helps support these success factors is interface management. As illustrated above, large, complex, modular-based projects struggle to achieve on-budget, on-time performance, and mismanaged interfaces are a key factor in this. In offshore projects, interface issues account for up to 20% of total installed cost. These multidiscipline projects can easily include up to 75,000 task-related interfaces and thousands of engineering deliverables. Without established work processes to manage these thousands of interface-related issues, the risk of cost overruns and schedule delays increases dramatically. More and more project owners are recognizing interface issues as a significant risk to their projects and are actively pursuing interface management solutions to address this risk. Thankfully, the treacherous waters of offshore project management do not need to be navigated alone (pun intended). Interface management systems are specifically developed to help manage interface issues prevalent within these projects and help to ensure your project comes in on-time and on-budget. An interface management system can help you influence a project’s success by:
The research shows (and any seasoned project manager can tell you) there is no single factor affecting cost or schedule overruns on projects, however, proactively managing interfaces has been proven to mitigate some of the known risks with megaprojects. A relatively small, up-front investment in a dedicated interface management solution can save hundreds of thousands of dollars in re-work down the road.